Daytime road resurfacing projects in Beaufort County
BEAUFORT, Sc. (WTOC) - Beaufort County transportation leaders will begin daytime road resurfacing beginning Monday July 14, from 7 a.m. to 5 p.m. daily.
The schedule is as follows:
- Wednesday, July 16- Monday, July 21
- Columbia Drive, Smalls Hill, Smith Road, Jaspertone Circle & Dolphin Drive
- Tuesday, July 22-Thursday, July 24
- Adams Circle & Jackson Street
- Friday, July 25-Tuesday, July 29
- BE Wheatly (duration does not necessarily mean weekend work – weather and other factors will dictate if Saturday work is required)
The resurfacing operations are funded by the Beaufort County Transportation Committee.
During construction, lane closures, road cones and signage will be visible to direct traffic safely. Motorists and residents should be prepared for lane closures and are encouraged to use extra caution when approaching work zones.
All work is weather permitting.
Recent Posts

Building codes help, not hinder, housing affordability

Dave Turley’s First Alert Weather forecast for Sunday, August 23, 2026

Graham campaigns in Beaufort ahead of Tuesday’s GOP runoff

Beaufort County head-on crash leaves one dead

Hampton County Fire-Rescue respond to tractor fire

1 teen found and in custody, search for 2 more in Beaufort continues

Deputy injured, 2 in custody after pursuit in Appling County

NEXA Lending acquires UMortgage, adds Anthony Casa to exec team

2 injured in shooting near Mixon Street in Yemassee

‘The people in power need to be held accountable’: Community reacts to Savannah Flock camera arrests